Fixed price or time and materials: the question comes up as soon as you have software built. Most answers compare two ways of billing, and they assume that a fixed price locks in both the price and the feature list. Yet there are two kinds of fixed price. A fixed price with fixed scope puts a price on a written specification. A fixed-budget, flexible-scope contract fixes the budget and the problem to solve, and lets the features that address it evolve.
Fixed scope and time and materials have one thing in common: both rest on a prediction. The first predicts the cost of a feature list. The second predicts a number of days.
And requirements do change. When Microsoft measures the effect of its ideas through controlled experiments, only one in three improves the target metric. One third has no effect, one third makes it worse, according to Ronny Kohavi, who led Microsoft’s experimentation team, and Stefan Thomke, a professor at Harvard Business School. Nobody knows in advance which ones. You find out through use.
Under a fixed price with fixed scope, the provider commits to delivering a list of features, described in a written specification, for a price set at signing.
Under time and materials, the provider supplies people and bills the time they spend, by the day. What is set at signing is the day rate.
Under a fixed-budget, flexible-scope contract, the price is set, and so is the problem to solve. What stays flexible is how it gets solved: the features that are developed.
So a fixed-scope contract locks in the total price and the list. Time and materials sets only the day rate. A fixed-budget contract locks in the budget and the problem, not the list. To see who carries the risk, you have to look at how each one arrives at its numbers.
Everything starts from the specification. The provider breaks the list down into tasks, then estimates each task in days of work. They add it all up. They multiply by their rate. Out comes a price.
That price rests entirely on estimates. And an estimate is still a guess about work that has not been done yet. Vasco Duarte has looked at what those guesses are worth. He has worked in software since 1997 and was one of the people who drove agile adoption at Nokia and F-Secure. In his book NoEstimates, he reports data he collected at one company between 2001 and 2003, across seventeen projects. The average delay against the estimate was 62%. A project planned for three months took nearly five.
A provider who commits to a price knows this risk, and builds it into the figure. Evan Leybourn, co-founder of the Business Agility Institute, wrote a guide to agile contracts, How Much Does This Cost? In it, he explains that when price and scope are both fixed, the provider raises the contingency before submitting the quote. Tomas Rybing, author of Applied Capacity Planning With NoEstimates (2015), describes the same practice: a gut-feel multiplier applied to the estimate, to allow for the obstacles you know you will hit without knowing which ones. He mentions values such as 30%, or doubling it. These margins generally run from 30% to 250%, depending on the project and the industry.
Duarte shows where this stops working. A margin that is too wide makes the bid more expensive than the competition’s. A smaller margin is not enough either, because of Parkinson’s law. Once the time is granted, work tends to expand to fill it. A task that runs longer than planned eats its share of the margin, then a little more. A task that finishes early does not give the time back: it is lost waiting for the next one to start. By the end of the project, there is no margin left, and the delay comes back anyway. In Duarte’s view, a margin thus quietly gives everyone permission to be late.
The schedule follows the same logic as the price. The estimated tasks are put in order, often in a Gantt chart, and grouped into milestones. Each milestone has its date. Acceptance testing comes at the end, once everything has been delivered.
This schedule is detailed, and that is what makes it hard to change. Duarte points this out: changing the order of the work in a detailed plan means reworking all of it: the sequence of tasks, their content, and who does them. The simpler the plan, the more easily it absorbs change.
Yet the list is written before the software exists, on the day you know least about how your users will work with it. Along the way, requirements shift. A planned feature is no longer needed. Another one, which nobody had thought of, becomes urgent. Each of these discoveries falls outside the signed list. It goes through a change request, priced separately. It becomes a change order, and the client pays for it.
The gaps can be large. Across 4,677 IT projects, the actual cost averages 1.8 times the estimated cost, or 80% more, according to a 2022 study by Bent Flyvbjerg, a professor at the University of Oxford, and his co-authors. That average is pulled up by a minority of projects with extreme overruns: in the same sample, the median overrun is close to zero. But nobody knows, on the day they sign, which side their project will fall on.
On paper, a fixed price with fixed scope protects the client from estimation error. The price is signed, and it is up to the provider to absorb the gap. In practice, that protection does not hold up well. The contingency, which the client pays for in the quote, gets used up along the way, as Parkinson’s law shows. And whatever is discovered during the project that is not on the signed list comes back as a change order, which the client also pays for. So the client ends up paying more than the signed price. The date fares no better: for this case, where price and scope are fixed, Leybourn advises keeping the delivery date flexible and moving it as far as needed.
When price, scope and date are all fixed, Leybourn is blunter still. His advice is to “Cancel the work”. In his view, such a project is not suited to an agile approach, and even when run with a traditional method, it is likely to fail without some flexibility.
Our conclusion: when price, scope and date are all locked, one of the three ends up giving way. The budget is exceeded, delivery slips, or features get dropped.
Under time and materials, the price of a day is known. The number of days is not.
The starting budget is still built the same way as for a fixed-scope contract: someone estimates the number of days needed and multiplies it by the rate. The difference is that this figure commits no one. It is a provisional budget. The invoice follows the days actually worked, backed each month by a timesheet.
If the work takes twice as long as planned, it costs twice as much. The estimation risk sits entirely with the client.
Leybourn nonetheless sees it as the most flexible contract. The client can stop as soon as what the rest would cost exceeds what it would bring in. To limit spending, he describes a capped variant, where the cap has to stay high enough for the investment to remain worthwhile. The budget becomes a limit again, but a limit that was, once more, estimated.
This is the strength of time and materials: the list stays open to change. The client changes priorities whenever they like, with no change order. Many teams then work in short iterations, two weeks for example. They estimate each item in story points, measure how many points they complete per iteration, and work out a date from that.
Duarte points out the flaw in this mechanism: as they go, the team understands the work better. Some teams end up re-estimating everything that is left several times over, and the date they had worked out no longer holds.
He proposes something else. Stop estimating the size of items, and slice them small enough that they look alike. Count how many are finished each week. Extend that pace to forecast what comes next. He adds that work discovered along the way is not scope creep: it is value discovered. And he argues for a principle that turns the fixed-scope contract upside down (ch. 2): fix the time and the cost, and let the list vary.
Duarte himself no longer talks about estimating; he talks about forecasting. These tools are the best available when you are forced to predict. They limit the damage, and they push towards a flexible scope. But they still rest on a form of estimation: they assume that the past pace holds for what comes next. A guess about the future has been swapped for an extrapolation from the past.
Lastly, what time and materials sells is days. Nothing in the model requires usable software to be in your users’ hands at every step. And the provider has to keep authority over the people it supplies. When the client directs their work day to day, the provider may count as an employment intermediary under UK tax rules: HMRC’s agency rules apply to anyone who supplies workers to a client, unless the worker is shown to work without anyone, the provider or the client, having the right to supervise, direct or control the manner in which they work.
For Leybourn, a contract is defined first of all by the level of risk each party agrees to carry. Fixed scope and time and materials present themselves as opposites. Yet they start from the same move: estimating the work before doing it. The fixed-scope contract turns that estimate into a price. Time and materials turns it into a provisional budget, then tries to keep visibility: timesheets, tracking of the days used, a recalculated end date.
Why do we cling to these forecasts? Frédéric Leguédois, an agile coach and trainer, answers in his talk “Éloge de la simplicité” (In Praise of Simplicity): in the face of uncertainty, a schedule is a reassuring mental picture. “A schedule is an organisational comfort blanket” (our translation).
A comfort blanket soothes. It protects against nothing. A schedule recalculated every week gives the impression of steering the budget. The budget itself keeps following what the work actually costs.
The fixed price as such is not the problem. The problem is fixing the budget and the feature list at the same time. A feature list with dates attached, drawn up before work starts, is what Frédéric Leguédois calls a schedule. In the same talk, he says what he thinks of schedules: “A schedule is the list of everything we are sure not to be doing today” (our translation). He adds that a schedule gathers information that is “useless today” and “wrong from tomorrow” (our translation). Fixing both the budget and that list puts all the risk of uncertainty on one of the parties, and nobody can adapt any more. Fixing nothing, on the other hand, lets the budget drift.
That leaves one combination neither of them offers: fix the budget and the problem to solve, leave the scope that addresses it flexible, and stop predicting what cannot be predicted.
Think this is new? Cathedral builders already worked this way. A Gothic cathedral was built with whatever money came in: the income of the bishop and the canons, and the gifts and bequests of the faithful. When money ran short, work slowed down, and sometimes stopped for a long time.
Nor did they start with the façade. More often than not, they started with the choir, the part of the church where services are held. At Notre-Dame de Paris, work began in 1163. The high altar in the choir was consecrated in 1182, and a temporary wall separated the choir from the building site, so that ceremonies could go on there while the nave was being built. In Cologne, the choir was consecrated in 1322, seventy-four years after the foundation stone was laid. Work stopped around 1520 and only resumed in 1842, with around 60% of the cost paid by an association of donors. The cathedral was completed in 1880. In Beauvais, the money ran out before they could go beyond the choir and the transept: the nave was never built. In each of these cathedrals, people were using what had been built long before the rest existed.
Leybourn describes a related form: a price fixed per week or per iteration, a fixed date, a flexible feature list. The price no longer comes from an estimate: “The cost is effectively budgeted, instead of estimated”. He still measures the rate at which items are accepted, though, to forecast how many will fit in the time available. That remains a prediction.
This is where our model parts ways with it. It is a fixed price: a fixed monthly budget, with no end date to forecast and no pace to extend. What is fixed is the budget and the problem to solve. What stays flexible is the scope, that is, the features that address the problem. Each one is an experiment, framed by the same question.
How the budget is set. The budget does not start from a feature list to price. It starts from the time you decide to invest in developing your software and in adapting it as your business evolves, weighed against what going without it costs you.
How the work is planned. There is no Gantt chart, no dated milestones, no pace extended to forecast an end date. The approach predicts what is predictable: the monthly budget and the development days per month. It does not try to predict the unpredictable: what your users will do with a feature before they have it in their hands. It fits what Frédéric Leguédois, in his training course “Un retour à l’essence de l’Agilité” (A Return to the Essence of Agility), calls “working without projection” (our translation). And it asks a single question: what is the most useful thing to do now?
Your application is usable within a month, with a handful of essential features: your users start using it straight away, and it is their use that decides which features to develop next. Every day, you see it move forward on your staging environment.
Once a feature has passed acceptance and gone live, it is judged by how your users respond to it, and we decide on the next ones with you right away, for as long as you wish. When their use of a feature teaches us something, we apply that lesson the same day. A living application is never finished: once you stop developing it, all it gets is security fixes and updates to the components it relies on, and that is an application that is dying.
What happens when requirements change. The problem stays the same. What changes is how it is solved, and nothing has to be renegotiated. The feature that is no longer needed comes off the list. The one that becomes urgent moves to the front. The budget does not move. What we develop, on the other hand, follows what your users teach us by using it.
That does not make it time and materials. What you receive, release after release, is not a timesheet. It is software your users work with.
We develop your bespoke application on a fixed budget, invoiced at the end of each month for the work done. That budget is agreed before work starts, together with the problem to solve.
Your budget buys ongoing work to ease this problem, starting on the first day of development. We aim to solve it completely, but we cannot guarantee that or put a date on it. You do not wait for that day for the problem to start easing. With every release, you see what the work has produced, and you decide whether to continue. You can terminate the contract in writing at any time, without justification.
A results guarantee is there to protect a client who cannot leave. Here, you can leave every month.
So that what worked last month still works this month, we apply a zero-regression guarantee: every regression is fixed and covered by an automated test so that it does not come back, at no extra cost.
Under a fixed price with fixed scope, the provider carries the estimation error on the signed list. The client carries changing requirements, one change order after another.
Under time and materials, the client carries both. A change needs no change order, but every extra day is added to the invoice.
Under a fixed-budget, flexible-scope contract, there is no estimate left to overrun. The budget is known before work starts, and it holds, because nothing depends on a prediction. Changing requirements change what gets developed, not what gets paid. And the client can terminate the contract in writing at any time, without justification. So their technical partner has every reason to do the work well: otherwise, the client ends the contract. The more useful the software is to the client, the more reason they have to continue, and the more reason their technical partner has to take care over the work.
A fixed price with fixed scope still suits a need that will not change. Work you repeat the same way every time becomes predictable. Software, by contrast, is always built for the first time.
Under a fixed price with fixed scope, the price is the sum of estimates made before work starts, on a feature list whose relevance nobody can know. The actual cost often ends up above the planned budget, and pays for very few developed features that bring any real business value. We explain why the cost exceeds the budget in our article on budget overruns.
Our guide covers these sources in detail. You will also find the questions to ask before signing a quote for developing your custom tool.
Do you need software built, or do you have a tool that no longer keeps up with your business? Shall we talk?
End of SaaS, SaaSpocalypse: since 2024, the claim keeps coming back. What you pay for when you pay for software, and what we have known for over forty years.
Bespoke or off-the-shelf software? Re-keying, unused features: the signs that your teams are adapting to the tool, and when to buy rather than build.
Technical partner for SMEs: fractional CTO, agency, managed IT services or integrator. What each one does, and what you should own at the end.