Waterfall or agile: the question comes up as soon as you have software built. It is usually answered by comparing two project management methods, with their stages, their meetings and their documents. The difference lies elsewhere. At the start of a project, nobody knows exactly what your users will need. You can try to foresee it, write it down in a specification and stick to it. Or you can learn it along the way, by putting the software in their hands, and adapt to what you discover.
A predictive approach decides in advance what will be built, and when. An adaptive approach decides as it goes, based on what it learns. And many practices that carry the name agile today are still predicting, by other means.
The predictive approach: the plan comes first
The waterfall model and the V-model share one principle. The stages follow one another, from requirements through to operations, and each one starts from the output of the one before. The plan is fixed at the start. Testing comes after the build.
This model has a history, and it begins with a warning. In 1970, Winston Royce, an engineer at TRW, an American aerospace and defence group, published a paper in which he drew this sequence of stages. Just below it, he wrote: “I believe in this concept, but the implementation described above is risky and invites failure.”
He explains why. The testing phase, placed at the end, is the first point at which the system’s actual behaviour can be observed. If that behaviour does not meet the constraints, the design has to be revisited. Development then goes back to where it started, and, he writes, you can expect up to a 100% overrun in schedule or cost.
Yet Royce considered the approach sound, on one condition: adding five steps to it. Among them, doing the job twice, with the first version serving as a simulation of the second. And involving the customer, formally and continuously.
Craig Larman, then chief scientist at the consulting firm Valtech, and Victor Basili, professor of computer science at the University of Maryland, traced what happened next. The US Department of Defense standard DOD-STD-2167 required a strict, document-driven, single-pass waterfall model. In the late 1980s, the Department of Defense experienced significant failures in its software acquisitions. Nearly ten years later, the standard’s main author said he regretted writing it: he had not known about iterative development at the time, and he would have strongly recommended it. In December 1994, MIL-STD-498 replaced the revised version, DOD-STD-2167A. It describes development in several successive builds, each of which implements part of the planned capabilities.
A predictive approach still suits a need that will not change. Work you repeat the same way every time becomes predictable. Software, by contrast, is always built for the first time.
What agile was meant to be
In February 2001, seventeen specialists in iterative methods met in Utah. The result was the Manifesto for Agile Software Development. Its title says what it is about: software development, not project management.
Its four values fit in four lines. One of them: “Responding to change over following a plan”. Two of its principles point the same way: “Welcome changing requirements, even late in development” and “Working software is the primary measure of progress”.
In this text, agile is not a method. It is an approach: deliver software that works, see what it achieves, and change direction when what you learn calls for it.
When agile still predicts
A good share of what is practised under that name today brings prediction back in.
Story points. Ron Jeffries, one of the signatories of the Agile Manifesto and co-author of Extreme Programming Installed, tells how they came about. His team estimated in “ideal days”, which stakeholders read as calendar days. To clear up the confusion, the team renamed them “points”. In 2019, he wrote: “I like to say that I may have invented story points, and if I did, I’m sorry now.”
Velocity. Many teams estimate each item in story points, measure how many points they complete per iteration, and work out a date from that. Vasco Duarte points out the flaw. He was one of the driving forces behind the adoption of agile at Nokia and F-Secure. In NoEstimates, a book that shows how to track a project’s progress without estimating anything, he explains that as the team moves forward, it understands the work better. Some teams then end up re-estimating everything that is left, several times, and the date worked out from it no longer holds. He comes back to this point in an interview published in 2015 by InfoQ, a news site for software developers.
Scaling frameworks. SAFe (Scaled Agile Framework) is a framework designed to organise many “agile” teams at once. The teams get together every 8 to 12 weeks to plan the next period as a group. Among the outputs of that session, the SAFe documentation lists a board showing feature delivery dates and what has to be delivered before what.
The SAFe Delusion site, run by a group of agile practitioners, brings together ten documented cases of organisations that adopted SAFe, across different sectors and countries, backed by 74 sources. One concludes that the framework was more of a hindrance than a help; another saw real improvements and happier customers after leaving it. According to the authors, companies that adopt SAFe often lose most of what makes agile practices work, reproduce the weaknesses of traditional methods in a more pronounced form, and spend a great deal of time learning outdated practices. These effects come from the way the framework is designed, not from the people who apply it or the coaches who teach it.
I have lived through it. In an organisation that ran on SAFe, I joined a team for six months, on a €10 million project planned over two years. Around the fourth month, we were told the project had been cancelled. I tell this story on the About page. SAFe is a con: an entire industry living off the sale of training courses and certifications whose only use is to land jobs in large companies that run on hot air.
Faced with these frameworks, Bryan Finster chose humour. He now maintains MinimumCD.org, a site dedicated to the basic practices of continuous delivery. He launched SADMF, short for Scaled Agile DevOps Maturity Framework: a fake scaling framework, presented with all the seriousness of the real ones. It promises “Enterprise DevOps transformation without the risk of culture change!”, achieved through more ceremonies, comprehensive documentation and clearly defined roles. Its practices include “Strategic Test Deferral” and “Precise Forecasting and Tracking”. Its roles include a “Review Board Review Board”: a board that reviews the review boards. It is a caricature of what this article describes: a framework that promises agility without changing anything about how people work, and that adds meetings, documents, committees and forecasts.
As it happens, I am SADMF certified myself. Wondering what that means? A certification every bit as much of a parody as the framework that awards it.
Martin Fowler, one of the signatories of the Manifesto, named this drift in 2018: “faux-agile: agile that’s just the name, but none of the practices and values in place”.
NoEstimates: counting instead of estimating, more honest, still predictive
Some teams have stopped estimating. Duarte proposes slicing the work into items small enough to look alike, counting how many are finished each week, and extending that pace to forecast what comes next. Allen Holub, a software architect and trainer, helps companies move towards agility. In his introduction to NoEstimates, he recommends the same method. He calls these projections, and the word comes from this school: you extend a measurement instead of guessing.
It is more honest than a guess. But it is still a prediction. A guess about the future has been swapped for an extrapolation from the past.
The question has not changed: how fast will we go, and when will we be done?
The adaptive approach: no longer depending on prediction
An adaptive approach does not ask that question. It asks a different one: what is the most useful thing to do now? And it answers with what is known at that moment. Not with what was imagined on the day of the quote.
Dave Farley, a software engineer and co-author of the book Continuous Delivery, is blunter in his video “How To Estimate Software Development Time”: he does not believe in estimates, and says we should not either.
Frédéric Leguédois, an agile coach and trainer, makes the same point in his talk “Éloge de la simplicité” (In Praise of Simplicity): “A plan is the list of everything we are sure we will not be doing today” (our translation).
Adaptive does not mean nothing is planned. The approach predicts what is predictable: the monthly budget and the development days per month. It does not try to predict the unpredictable: what your users will do with a feature before they have it in their hands.
There is a reason for this distinction. When Microsoft measures the effect of its ideas through controlled experiments, only one in three improves the target metric. One third has no effect, one third makes it worse. That is what, in an article published in 2017, Ronny Kohavi, who led Microsoft’s experimentation team, and Stefan Thomke, a professor at Harvard Business School, measured. Nobody knows in advance which ones. You only find out once they are in use. A feature is judged by its use, once it is delivered. An idea for an application, on the other hand, can be tested before it is even developed: that is what an MVP is for, a test rather than a product, which sometimes needs no code at all.
What this means for custom software
With a predictive approach, the feature list is fixed at the start, along with the price and the date. Yet the list is written before the software exists, on the day you know least about how your users will work with it, at the risk of spending months building something no user ever works with. Every discovery made along the way becomes a change order. Every change order widens the gap with the quote. Dave Farley explains it in his video “Fighting User Requirements That CONSTANTLY Change”: developing software means learning, as you go, what it needs to do. Writing better requirements is not enough.
Our agile development approach starts from the other end. What is fixed is the budget and the problem to solve. What stays flexible is the scope, that is, the features that address the problem.
Your application is usable within a month, with a few essential features: your users start working with it straight away, and how they use it determines which features come next. A living application is never finished: once you stop evolving it, all it gets are security patches and updates to the components it runs on, and it is an application that is slowly dying.
Take a rover sent to explore Mars. Designing and building it is expensive, and once it has been launched, there is no getting it back. So mistakes must be avoided at all costs, because once it is on its way, nothing can be fixed. Before launch, it is studied, built and tested, even if that means failing, to check that it is on target. What was learned then goes into the next version: Perseverance, launched in 2020, reuses many components from Curiosity, its predecessor, but its wheels were redesigned, and testing showed that they held up better on rocks and sand. Building on each generation like this takes a design that is easy to change: that is what quality means. An everyday application calls for the same rigour, to avoid waste, but its context changes all the time: regulations, habits, the way people consume. It is as if you had to send a rover to Mars every day, with space and Mars changing from one day to the next.
Once a feature has been signed off and released, it is judged on how your users respond, and we decide the next ones with you right away, for as long as you wish.
We develop your bespoke application on a fixed budget, invoiced at the end of each month for the work done. That budget is agreed before we start. The feature list, on the other hand, takes shape through use. It is a fixed price, but not a fixed-scope one.
When requirements change along the way, what does that change cost? The answer depends on the contract, and our article on fixed price and time and materials compares a fixed price with fixed scope and fixed budget, time and materials with fixed scope and a flexible budget, and a fixed price with a fixed budget and flexible scope. Then there is the question of price. Under a fixed price with fixed scope, the price is the sum of estimates made before starting, on a feature list whose relevance nobody can know. The real cost often ends up above the planned budget (according to a 2022 study by Bent Flyvbjerg, a professor at the University of Oxford, and his co-authors), for very few features built that bring genuine business value: at Microsoft, as we saw, only one idea in three improves the target metric. Our article on budget overruns explains why.
Further reading
Our guide traces the history of the waterfall model in detail, along with what the creators of agile say about what it has become.